| Paths
& Sidewalks
Q.
Bike path on Willowdale needs repair. (Sept 06)
A. Response from Operations: Needs to be reconstructed/finished.
May look at this in 2008.
Response from Operations: Scheduled for 2008. (Oct 07)
Q.
Sidewalk in front of 36 Silver Birch – 7 years. (Sept 06)
A.
Response from Operations: Will check this spring and will inform
property owner on timeline for repair. (Sept 06)
Response from Operations:
Will look at this get back with a timeline to fix.
I have asked
for an update from operations on when this will be looked at. (Sept 07)
Response from Operations: Will be completed this year. (Oct 07)
Q.
Bikepath between houses on Marquis (between Marquis and 26th/Maryland).
Has been in bad shape for 10 years and nothing has been done with
it. (Aug 06)
A.
Response from Operations: It needs to be reconstructed. We will
look at in 2008. (Sept 06)
Response from Operations:
We are looking at doing significant repair to bikepaths in 2008. Will look at this then.
Response from Operations:
We are currently working on the path. Need to remove some trees that are too close to the path. (Sept 07)
Response from Operations:
Work has been completed. (Oct 07)
Q.
Bench between McDiarmid and Cherry needs bushes beside. (Sept 06)
A.
Response from Operations: We will look at in Spring. (Oct 06)
Response from Operations:
Will look at this get back with a timeline to complete.
Response from Operations:
Will be completed this fall. (Oct 07)
|